Cooloolabin Dam

DAM MODIFICATION

DATE

November – December 2015

LOCATION

Sunshine Coast QLD

CLIENT

Doval Constructions

VALUE

$ 280,000

Overview

Doval engaged Decotec to remove 200 tonne of concrete from the Cooloolabin Dam spillway crest to reduce the dam capacity due to modern safety constraints. The spillway was cut into 27 sections using diamond wire and then hydraulically split into a total of 80 sections, which were lifted out with a barge crane.

Decotec offered good solutions to problems, were co-operative in all dealings and a pleasure to work with…” Kevin Mattushek | Doval Contracts Manager